Holford Road

Date:
02/01/2011

Client:
Cubitt Theobold

Completed in 2011 for main contractor Cubitt Theobold, this Holford Road project exemplifies advanced basement construction using top-down methodology – a specialist technique allowing excavation and construction beneath an existing occupied residence. O’Sullivan Civil Engineering installed comprehensive temporary works to support the entire property structure during construction, combined with deep underpinning and mini piling for enhanced foundation capacity.

The scope included careful excavation beneath the house, precision formwork construction, and creation of a luxury swimming pool area complete with elegant floating concrete steps.

This project demonstrates our expertise in complex residential basement construction using sophisticated engineering techniques.